Preliminary review of the permit package indicates the following proposed changes:
An increase in the maximum daily tonnage received each operating day from 1,250 tons per day to 1,800 tons per day.
An increase in the maximum elevation of the landfill from approximately 50 feet mean sea level (MSL) to 80 feet MSL.
An increase in hours for Resource Recovery Operations from 6:00am to 10:00pm 7 days per week to 6:00am to 12:00am 7 days per week.
Allow a portion of the flat top-deck surface of the on-site landfill to be used for employee parking and equipment/truck parking.
Adding an additional inbound scale to existing scale house operations.
Constructing a new, two story office/administration building (approximately 6,400 square feet).